Bridge fence still not fixed over a year and a half of waiting!
Reported via mobile in the Structures (eg bridges, fencing, noise barriers) (NH) category anonymously at 20:38, Thursday 29 January 2026
Sent to National Highways less than a minute later. FixMyStreet ref: 8798157.
The bridge has still not had its fencing fixed even after a year and a half since it happened. Reduced speeds causing issues. The barrier towards the on coming slip from emsworth has been repaired but the other area left and forgotten?
The road has been closed multiple times full and partially over this period and still no one has sorted it out. It's getting ridiculous. It needs doing ASAP before someone has a crash into that section and goes through the temporary mesh that does nothing.
Not to be rude by any means it's just getting silly now.
Updates
-
Thank you for making your report.
On the A27 in this area, a temporary speed limit has been installed until repairs to a damaged parapet can be completed. The reduction in speed is to avoid any further accidents involving the public or any more damage to the parapet. We’re looking to complete a permanent repair at the earliest opportunity, but unfortunately we don't yet have a date for this.
Although we always aim to complete repairs as quickly as possible, timescales do vary as we try to minimise disruption to customers by combining activities into single closures and always ensuring the safety of our people.
Kind regards National Highways
State changed to: In progress
Posted by National Highways at 11:31, Monday 2 February 2026