Timings on the lights changed

Reported via mobile in the Traffic lights (NH) category anonymously at 13:17, Tue 19 September 2023

Sent to National Highways less than a minute later. FixMyStreet ref: 5009864.

Hi for the past month or just a bit more each morning I have noticed the traffic is so much worse by lights on the A 5 island ( near to A34/A460) it is only on green for west bound traffic for 15 seconds so that traffic backs up to churchbridge island and back down th A 5 and through Great Wyrley.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Traffic lights are changing far too quickly, causing a traffic jam around the rest of the islands at Churchbridge. Cars and lorries are blocking exit road from A34 so causing another build up along the Walsall Road to Great Wyrley

    Posted by Linda at 17:56, Tue 19 September 2023

  • The timing on these lights is horrendous. Only allowing 6 or 7 vehicles through the green light before changing back to red and it is causing chaos on the A5 and A34 every single morning, accident waiting to happen!!

    Posted anonymously at 00:38, Wed 20 September 2023

  • Traffic lights need to be altered causing major jams down to orbital from a34 great warley and ftom brownhiĺls .timing of lights was altered by workmen 4 weeks sgo something neefs to be done asap as a major accident will occur .is sldo stopping people getting to retailers on the parks .It ia also causing jsms to m6 at peak times

    Posted anonymously at 16:37, Wed 20 September 2023

  • The traffic lights have been out all together today and the traffic is now moving freely, demonstrating that the traffic management by lights out of sync has been the cause of severe disruption of the last month - when reinstated, the traffic light timings need to reviewed for most efficient traffic flows and/or revert back to timings in place in June/July. A failure to do so would be negligent and inconsiderate to road users.

    Posted anonymously at 11:52, Fri 22 September 2023

  • Thank you for contacting National Highways.

    We're aware of the issues at these traffic lights which were due to a resurfacing scheme in the area. The work was started in August when the traffic loops for these lights were first cut, resulting in the tailbacks of traffic. Unfortunately, due to an emergency these works had to stop and weren't completed. We're due to return to the area by the end of September subject to road space availability to complete the resurfacing. Upon completion of the resurfacing the traffic lights will operate as normal.

    Kind regards

    National Highways

    State changed to: Action scheduled

    Posted by National Highways at 15:20, Tue 26 September 2023

  • Please change back the traffic light timing to its original scheduled timing. The lights are causing havoc with the local traffic and traffic entering from the A5 westward, it’s snarling up traffic from all approaches. It is chaos, please change light timing back

    Posted by Ian gripton at 09:12, Mon 2 October 2023

Provide an update

Please note that updates are not sent to National Highways. Your information will only be used in line with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a National Highways Report a problem password?