Large number of pot holes along CL and edge or carriageway

Reported via desktop in the Pothole (NH) category anonymously at 22:17, Mon 23 January 2023

Sent to National Highways less than a minute later. FixMyStreet ref: 4163908.

On the southbound carriageway there are multiple potholes especially where the old road markings and studs were removed. This is present along both the NB and SB of the scheme and is getting worse by the day. Unable to avoid due to the already congested and narrow temporary lanes.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting this issue to us via FixMyStreet. We appreciate the time you've taken to contact us about this.

    Costain Jacobs working on behalf of National Highways apologise for any inconvenience caused by the condition of the carriageway.

    The team have recently filled in several potholes but due to the recent bad weather these have opened again.

    Our Traffic Safety Control Officers (TSCO’s) patrol the scheme regularly and report any carriageway defects to the traffic management team. The team have a plan in place to repair potholes as they are identified and continue to fill them in as soon as possible.

    When the widening of the A1 is complete and we have the extra lane either side of the carriageway, we'll be resurfacing all lanes as part of the A1 Birtley to Coal House scheme.

    Kind Regards, National Highways on behalf of Costain Jacobs

    State changed to: Fixed

    Posted anonymously at 22:33, Wed 5 July 2023

This report is now closed to updates from the public. You can make a new report in the same location.