Back to all reports

Sequencing

Reported via desktop in the Traffic lights category anonymously at 18:14, Tuesday 19 October 2021

Sent to National Highways less than a minute later

Disparity between length of “green” between mains lane and garstang new road leading to delays of 30+ mins leaving poulton on garstang new road at all times of day. Causing major issues for all residents using this main route and has been for many weeks. NEEDS URGENT ATTENTION.

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • We appreciate your concerns and are grateful for you taking the time to report your observations. Our team delivering the A585 Windy Harbour to Skippool bypass scheme became aware of an issue recently with the traffic light timings. Failed sensors buried in the carriageway of the adjacent local authority road network, which are linked to our traffic lights here, were identified as the cause of the issue.

    We replaced the failed sensors in late September, but a subsequent assessment earlier this month revealed additional failed sensors (also on the local road network) linked to the traffic lights at the crossroads. The failed sensors were replaced overnight on 26 October and the traffic lights are now working as per their design. We plan to assess the suitability of the current timings in the near future and to adjust them where appropriate to suit am and pm peak period traffic flows.

    State changed to: Closed

    Posted anonymously at 14:03, Friday 29 October 2021

This report is now closed to updates. You can make a new report in the same location.