Road layout.
Reported via mobile in the Road markings (NH) category anonymously at 15:27, Sat 24 July 2021
Sent to National Highways less than a minute later. FixMyStreet ref: 2887923.
Road markings. No point in left hand lane being left only on to the A14
Updates
-
Bad lane markings are causing traffic chaos and dangerous situations. I have sat there for 30 mins today to get from Brampton to the roundabout to find people crossing into lanes all over the place. Please sort this out as it’s dangerous
Posted anonymously at 16:29, Sat 24 July 2021
-
The lights don't match. The queue to go across into huntingdon from brampton is 35 mins . It let's few cars out and then other set changes to red so queue still sitting there. Needs addressing as no other traffic in another direction
Posted anonymously at 06:19, Sun 25 July 2021
-
Thank you for contacting Highways England regarding Spittals roundabout.
The changes we’re making at the junction are a result of a design to make sure the correct destination signs are in place for the A1307 and A141. In order to manage the traffic, rather than closing the junction completely, we’ve done the work in phases around the roundabout. The road marking layout on the eastbound approach to Spittals is the last phase which is due to be finished early this week. Also, once all our changes are complete, a road safety audit will be done to highlight if there are any safety concerns which need addressing.
Lane 1 is now a dedicated left hand filter lane, solely intended for drivers wishing to exit Spittals roundabout and head northbound along the A1307 towards the A1M. Lanes 2 and 3 are for drivers continuing to travel on the A141 eastbound, or exiting Spittals roundabout to head southbound along the A1307.
As with any changes to the road layout on our SRN, we have installed temporary signs on the approach to Spittals roundabout, advising that the road layout has changed. As a temporary solution, we’ve also masked off the incorrect information on the approaching signs while replacement signs are being obtained. This ensures that the information on the signs matches the road markings on the approach to the roundabout, which should make it clear for approaching drivers which lane to take for their journey.
We apologise if these temporary measures have caused some confusion and not been very clear. We’re finishing the work by installing lane markings on the roundabout early this week and the straight ahead arrow in the inside lane will be hydro-blasted.
We have also recently discovered an issue on the controller that runs the traffic signals and resolved this yesterday. We hope this has improved the traffic light issue at the roundabout.
Thank you again for contacting us
Kind Regards Highways England
State changed to: Closed
Posted anonymously at 12:51, Wed 28 July 2021
This report is now closed to updates from the public. You can make a new report in the same location.